Questions version 4 du Pmbok Cliquez sur la fleche “réponse” pour afficher la réponse

The tools and techniques used in the initiation process are: A. Product analysis
 B. Project Develop Schedule C. Expert judgment
 D. Project budget Answer: C
 Explanations:
Expert judgment is required in the initiation process Likely schedule durations for Estimate Activity Durations are available from historical information that is derived from the following sources except: A. Commercial duration databases B. Project Read More

Questions examen PMP série 3/4

Questions examen PMP série 3/4

Questions examen PMP série 3/4

Questions version 4 du Pmbok Cliquez sur la fleche “réponse” pour afficher la réponse

A _______ is a series of actions bringing about a result. A. Project plan B. Process
 C. Schedule D. Flowchart Answer: B Explanations: Process What involves determining what quantities are to be used to perform project activities. A. Resource planning B. Estimate Costs
 C. Determine Budget D. Control Costs Answer: A
 Explanations:
Resource planning:Planning, identifying, documenting, and assigning project roles, responsibilities, Read More

Questions examen PMP série 2/4

Questions examen PMP série 2/4

Questions examen PMP série 2/4

Questions version 4 du Pmbok. Cliquez sur la fleche “réponse” pour afficher la réponse

Question: Which is not input to Define Activities: A. Work breakdown structure B. Product description
 C. Constraints
 D. Assumptions Answer: B
 Explanations:
Define Activities - Inputs: Work breakdown structure , Constraints , Assumptions and Organizational Process Assets . Question: When the project team directs staff assignments, what is not considered in the selection of a staff? A. Read More

Questions examen PMP série 1/4

Questions examen PMP série 1/4

Questions examen PMP série 1/4

Depuis début aout, les certifications PMI reposent sur la version 5 du Pmbok.

Quelques changements sont intervenus : - L’introduction d’un nouveau domaine de connaissance: les parties prenantes (jusqu’ici les processus étaient intégrés au domaine de la communication) - De nouveaux processus, dont 2 de contrôle : contrôle de la gestion de la communication et des parties prenantes - …

Mais pas de révolution entre les versions 4 et 5.

Read More